Home Page | Archives

NOVEMBER 25, 2019

SPECIAL MEETING

Stephanie DeAngelis
Stephanie DeAngelis
The Regency Tower Board of Directors Meeting was called to order by the Vice-President Stephanie DeAngelis at 5:05 p.m.

Treasurer John Amatulli
Treasurer
John Amatulli
Roll Call
Board Members Present: John Amatulli, Stephanie DeAngelis, Fern McBride

Attorney Emilie Gannon, from Kaye Bender Rembaum, was introduced

Fill Board Vacancies

A motion was made by Stephanie DeAngelis to appoint Norm Harris, John LaPrade, Catherine Lenz and Heidi Weber to fill the Board vacancies. The motion was seconded. After Ms. DeAngelis shared information about each appointee, the motion was unanimously passed.

John LaPrade, Catherine Lenz and Heidi Weber took their seats at the table; Norm Harris joined on the phone.

Reorganize Officer Positions

John LaPrade
John LaPrade
Secretary Fern McBride
Secretary
Fern McBride
A motion was made by Stephanie DeAngelis to nominate John LaPrade to serve as Board President. The motion was seconded and unanimously approved.

A motion was made by John LaPrade to nominate Stephanie DeAngelis to continue serving as Vice-President. The motion was seconded and unanimously approved.

The next Board meeting will be held on Monday, December 2, 2019; time to be announced.

Adjournment - No further business, the meeting was adjourned at 5:21 p.m.

Fern McBride
Board Secretary

Click to Top of Page

COMMITTEE REPORTS

NOVEMBER 2019

Budget & Finance Committee
John Amatulli

On November 20, 2019, Treasurer John Amatulli released the October 31, 2019 Treasurer's Report and emailed copies to Regency Tower residents. Copies can also be downloaded from the password protected Concierge Plus website and are available to owners in the Regency Tower office (Click Here to Concierge Plus website).

Click to Top of Page

Construction Oversight Progress Review
Stephanie DeAngelis

Concrete Restoration Update: November 7, 2019

President Stephanie DeAngelis issues Concrete Restoration Progress Report
Stephanie DeAngelis
Dear Regency Tower Residents,

Building Column Shoring Completed
Building Column Shoring Completed
There are a lot of good things to report!

Regency Tower has received a very nice holiday gift. Between December 24 and January 2, residents will have access to the pool and the beach during the day - all week long. The contractor has kindly agreed to continue working but keep stack one out of commission during that holiday week - allowing safe access for everyone to utilize the pool and beach all week long.

The project is moving along on schedule and there have been no significant delays.

All of the column shoring for the column repairs for the front of the building is complete and now the work has begun on the column repairs.

Repairs in NW Garage
NW Garage Repairs Complete
Unit 101 Balcony Repairs
Unit 101 Balcony Repairs
The balcony for unit 101 will be completed next month with tile / knock down finish, and painting so that it can be viewed by all residents. Everyone will be kept informed about viewing the mock up as soon as it's complete.

The northwest corner of the garage repairs are now complete.

The contractor said that the work on the first four balcony stacks will be complete at the end of December - barring any major delays. After that, work on the window drops will begin on the North side of the building.

Balcony Stacks 1 through 4
Balcony Stacks 1 through 4
We received an interesting proposal for shortening the project by as much as six weeks. It involves a new process for priming the balconies after the concrete is poured which allows the concrete to dry much quicker moving the entire process along faster. The board is waiting for a written estimate before proceeding with a vote.

We’re told the balcony tiles are on their way and should be here within the next couple of weeks. That timing works well with the progress of the project.

NOTE: After January 2, 2020, beach access will again be limited to weekdays after 5pm and weekends, and pool access will be limited to weekends until further notice.

Thank you again to everybody for your patience during this restoration project.

Regards.

Stephanie

Stephanie DeAngelis, LCAM
Acting President
Regency Tower